mediumMultiple SelectObjective-mapped
PK0-005 Practice Question: A project manager is reviewing change requests
A project manager is reviewing change requests. Which THREE types of changes would be subject to integrated change control?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule change
Change control applies to any change that affects the project baselines, including scope, schedule, cost, and quality.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Schedule change
Why this is correct
Schedule changes require formal change control.
- ✓
Scope change
Why this is correct
Scope changes require formal change control.
- ✓
Cost change
Why this is correct
Cost changes require formal change control.
- ✗
Office supply order
Why it's wrong here
Routine supply orders are not changes to baselines.
- ✗
Team member vacation request
Why it's wrong here
Vacation requests are operational and do not affect baselines.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.