PK0-005 Practice Question: A project manager is reviewing change requests

A project manager is reviewing change requests. Which THREE types of changes would be subject to integrated change control?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule change

Change control applies to any change that affects the project baselines, including scope, schedule, cost, and quality.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule change

    Why this is correct

    Schedule changes require formal change control.

  • Scope change

    Why this is correct

    Scope changes require formal change control.

  • Cost change

    Why this is correct

    Cost changes require formal change control.

  • Office supply order

    Why it's wrong here

    Routine supply orders are not changes to baselines.

  • Team member vacation request

    Why it's wrong here

    Vacation requests are operational and do not affect baselines.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.