mediumMultiple Choice

PK0-005 Practice Question: A project manager is updating the project…

A project manager is updating the project schedule and notices that the critical path has changed due to a delay in a key task. Which document should the project manager update first to reflect this change?

⚠ Common exam trap

The PK0-005 exam often tests the principle that the project schedule is the primary document for time-related changes, and candidates mistakenly update the issue log or risk register first because they confuse a schedule delay with a risk or issue that needs logging.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project schedule

The project schedule is the document that directly reflects the sequence, dependencies, and timing of tasks, including the critical path. When a delay causes the critical path to change, the schedule must be updated first to capture the new start and finish dates, float values, and path dependencies. This ensures the project manager has an accurate baseline for assessing impacts and communicating changes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Risk register

    Why it's wrong here

    The risk register tracks identified risks and responses, not task durations, dependencies or float, so it cannot record a shifted critical path. It is tempting because the delay may warrant a risk entry, but the schedule baseline and network diagram must be revised first.

  • ✗

    Stakeholder register

    Why it's wrong here

    The stakeholder register records people, their interests and engagement levels; it holds no schedule or critical-path data, so updating it cannot reflect the delay. It is tempting because changed dates affect communication planning, and the register would be revised when stakeholders are added or their influence shifts — not when task durations slip.

  • ✓

    Project schedule

    Why this is correct

    The schedule is the artefact that records activity dates, dependencies and float, so a critical path shift must be reflected there first. Updating it establishes the revised baseline from which other documents, such as the risk register, are then reconciled.

  • ✗

    Issue log

    Why it's wrong here

    An issue log tracks problems and their resolution status; it does not contain the network logic or float values that define the critical path, so the schedule itself must be updated first. Logging the delay as an issue is valid, but that records the problem rather than reflecting the recalculated path.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.