PK0-005 Practice Question: While monitoring and controlling, the project…

While monitoring and controlling, the project manager reviews earned value metrics and finds CPI = 0.8 and SPI = 1.1. What does this indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Over budget but ahead of schedule

CPI less than 1 indicates over budget; SPI greater than 1 indicates ahead of schedule. Therefore the project is over budget but ahead of schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Over budget but ahead of schedule

    Why this is correct

    CPI=0.8 (over budget), SPI=1.1 (ahead of schedule).

  • Under budget and ahead of schedule

    Why it's wrong here

    CPI < 1 means over budget, not under.

  • Under budget but behind schedule

    Why it's wrong here

    Both conditions are opposite.

  • Over budget and behind schedule

    Why it's wrong here

    SPI > 1 means ahead of schedule, not behind.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.