PK0-005 Practice Question: During project monitoring and controlling, the…

During project monitoring and controlling, the project manager calculates the cost performance index (CPI) as 0.8. What does this indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget

A CPI below 1 signifies that the project is over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is behind schedule

    Why it's wrong here

    This is indicated by SPI less than 1, not CPI.

  • The project is ahead of schedule

    Why it's wrong here

    CPI measures cost efficiency, not schedule performance. Schedule performance is measured by SPI.

  • The project is over budget

    Why this is correct

    CPI = EV/AC = 0.8 means for every dollar spent, only $0.80 of value is earned, indicating over budget.

  • The project is under budget

    Why it's wrong here

    A CPI less than 1 indicates over budget, not under.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.