Which cost estimation technique uses historical data from similar projects to estimate the current project?

⚠ Common exam trap

PK0-005 often tests the distinction between analogous and parametric estimating, and candidates confuse 'similar projects' (analogous) with 'statistical relationship/unit rates' (parametric).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Analogous

Analogous estimating uses historical data from similar past projects as the basis for estimating the current project's cost or duration. It is a top-down, expert-judgment technique that is fast and inexpensive but less accurate. The question's phrase 'historical data from similar projects' is the defining characteristic of analogous estimating.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Three-point

    Why it's wrong here

    Three-point estimation derives an expected value from optimistic, pessimistic and most-likely figures supplied by estimators, not from comparable historical project data. It is chosen when uncertainty is high and you want a probability-weighted estimate for a single activity.

  • ✗

    Bottom-up

    Why it's wrong here

    Bottom-up aggregates individual work-package estimates from the current project's own task breakdown, so it never references prior projects' actual costs. It is the right choice when detailed scope exists and analogous historical data is unavailable or unreliable.

  • ✗

    Parametric

    Why it's wrong here

    Parametric applies statistical relationships between project variables (such as cost per line of code) rather than directly reusing a similar past project's recorded costs. It suits projects with measurable, quantifiable parameters and reliable historical cost drivers.

  • ✓

    Analogous

    Why this is correct

    Analogous estimating derives duration or cost from historical data of comparable past projects, scaled for known differences. This matches the stem's requirement precisely, distinguishing it from parametric modelling, which uses statistical relationships between variables, and bottom-up estimating, which aggregates component-level detail.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.