Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

Which cost estimation technique uses historical data from similar projects to estimate the current project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analogous

Analogous estimation relies on historical data from similar projects.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Three-point

    Why it's wrong here

    Three-point uses optimistic, pessimistic, and most likely.

  • Bottom-up

    Why it's wrong here

    Bottom-up estimates individual work packages.

  • Parametric

    Why it's wrong here

    Parametric uses statistical relationships.

  • Analogous

    Why this is correct

    Analogous uses similar project history.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.