PK0-005 Project Management Concepts Practice Question
A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Over budget and ahead of schedule
CPI < 1 means over budget; SPI > 1 means ahead of schedule. Therefore, the project is over budget but ahead of schedule.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Under budget and behind schedule
Why it's wrong here
Both indices contradict.
- ✓
Over budget and ahead of schedule
Why this is correct
CPI=0.8 (over budget), SPI=1.1 (ahead of schedule).
- ✗
Over budget and behind schedule
Why it's wrong here
SPI > 1 means ahead of schedule.
- ✗
Under budget and ahead of schedule
Why it's wrong here
CPI < 1 means over budget.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.