A project manager is managing an agile project. The team uses iterative development and daily stand-up meetings. Which of the following is a key principle of agile project management?

⚠ Common exam trap

A common mix-up: candidates confuse 'customer collaboration' with simply having meetings, but the key distinction is that agile prioritizes ongoing, direct customer involvement over formal contract terms, which is a core shift from traditional project management.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Customer collaboration over contract negotiation

The Agile Manifesto prioritizes customer collaboration over contract negotiation, meaning the project team works closely with the customer to refine requirements and deliver value iteratively. In an agile project with daily stand-ups and iterative development, this principle ensures continuous feedback and adaptation rather than rigid adherence to a contract.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Comprehensive documentation

    Why it's wrong here

    Agile values working software over comprehensive documentation, so prioritising documentation contradicts its principles. It is tempting because documentation still has value in agile, and it is the correct answer for plan-driven methodologies such as waterfall, where baselined documents govern delivery.

  • ✗

    Following a detailed plan

    Why it's wrong here

    Agile welcomes changing requirements through iterative delivery, so a detailed upfront plan contradicts the scenario's daily stand-ups and short cycles. It is tempting because a plan is essential in waterfall projects, where scope is fixed and sequential phases make a comprehensive baseline schedule the correct artefact.

  • ✗

    Sequential phases

    Why it's wrong here

    Agile delivery builds working increments through repeated short iterations, so phases overlap and requirements emerge as feedback arrives; a fixed sequential hand-off between phases contradicts the sprint cadence and daily stand-ups described. Sequential phases belong to waterfall, where scope is frozen and each stage completes before the next begins — the right structure when regulatory sign-off or fixed-price contracting demands a single, fully specified delivery.

  • ✓

    Customer collaboration over contract negotiation

    Why this is correct

    Customer collaboration over contract negotiation satisfies the agile principle of prioritising working relationships with stakeholders above rigid contractual terms. In iterative development, requirements evolve each sprint, so continuous customer feedback shapes the backlog rather than fixed scope agreed upfront. This directly supports the stem's iterative delivery and daily stand-up cadence.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.