Courseiva
hardMultiple Select

PK0-005 Practice Question: A project manager is creating a risk register for…

A project manager is creating a risk register for a construction project. Which TWO fields are essential for calculating a risk score?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Probability

The risk score is typically calculated by multiplying probability and impact. These two fields are essential for determining the risk score.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Probability

    Why this is correct

    Probability supplies the likelihood dimension of the risk score, typically rated on a defined scale. Multiplied by impact, it produces the numeric exposure value recorded in the register, so without it the score cannot be calculated for the construction project.

  • ✗

    Risk ID

    Why it's wrong here

    A Risk ID is a unique identifier for tracking and referencing entries; it carries no likelihood or impact information, so it cannot feed a score calculation. It is tempting because every register entry needs one, but identification is administrative, not quantitative.

  • ✗

    Response Strategy

    Why it's wrong here

    Response Strategy records the planned mitigation, transfer, avoidance or acceptance action, which is chosen after the score is derived from likelihood and impact. It is tempting because it is a required register field, but strategy selection follows scoring rather than contributing to it.

  • ✓

    Impact

    Why this is correct

    Impact supplies the severity dimension of the risk score, quantifying the consequence if the risk occurs. Combined with probability through multiplication, it yields the numeric exposure value, making it essential for scoring each construction risk.

  • ✗

    Owner

    Why it's wrong here

    Owner assigns accountability for monitoring and executing the response, an administrative assignment independent of likelihood and impact values. It is tempting because every risk needs an owner, but ownership does not enter the multiplication that produces the risk score.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.