A project manager needs to communicate the project's progress to stakeholders with high power and low interest. According to the power/interest grid, which communication approach is most appropriate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Keep satisfied with periodic high-level updates.

Stakeholders with high power and low interest should be kept satisfied. They need sufficient information to ensure satisfaction but not overwhelmed with details.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Manage closely with frequent detailed reports.

    Why it's wrong here

    That is for high power/high interest.

  • Keep informed with regular status reports.

    Why it's wrong here

    That is for low power/high interest.

  • Keep satisfied with periodic high-level updates.

    Why this is correct

    Correct: Keep satisfied with minimal but sufficient info.

  • Monitor with minimal communication.

    Why it's wrong here

    That is for low power/low interest.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.