Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project planning, the project manager decomposes the project scope into smaller, more manageable components. What is the resulting document called?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work breakdown structure (WBS)

The WBS is a hierarchical decomposition of the total scope into work packages, forming the scope baseline.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scope statement

    Why it's wrong here

    The scope statement describes scope but does not decompose it.

  • Project charter

    Why it's wrong here

    The charter provides high-level scope, not detailed decomposition.

  • Work breakdown structure (WBS)

    Why this is correct

    The WBS breaks down scope into work packages.

  • Network diagram

    Why it's wrong here

    Network diagrams are used for schedule management.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.