Courseiva
Tools and DocumentationhardMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project manager is evaluating the project's performance using EVM. PV = $50,000, EV = $45,000, AC = $55,000. Which of the following is true?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget and behind schedule.

SV = EV - PV = -$5,000 (behind schedule). CV = EV - AC = -$10,000 (over budget). CPI = EV/AC = 0.818, SPI = EV/PV = 0.9.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is under budget and ahead of schedule.

    Why it's wrong here

    Both negative.

  • The project is over budget but ahead of schedule.

    Why it's wrong here

    SV negative means behind schedule.

  • The project is under budget but behind schedule.

    Why it's wrong here

    CV negative means over budget.

  • The project is over budget and behind schedule.

    Why this is correct

    SV and CV negative.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.