PK0-005 Project Life Cycle Practice Question
Which TWO documents are typically created during the project initiating phase?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Stakeholder register
The project charter and stakeholder register are created during initiating. The WBS and risk register are planning outputs; the status report is from monitoring and controlling.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Stakeholder register
Why this is correct
Created during initiating.
- ✗
Status report
Why it's wrong here
Created during monitoring and controlling.
- ✓
Project charter
Why this is correct
Created during initiating.
- ✗
Work breakdown structure
Why it's wrong here
Created during planning.
- ✗
Risk register
Why it's wrong here
Created during planning.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.