Which TWO documents are typically created during the project initiating phase?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Stakeholder register

The project charter and stakeholder register are created during initiating. The WBS and risk register are planning outputs; the status report is from monitoring and controlling.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Stakeholder register

    Why this is correct

    Created during initiating.

  • Status report

    Why it's wrong here

    Created during monitoring and controlling.

  • Project charter

    Why this is correct

    Created during initiating.

  • Work breakdown structure

    Why it's wrong here

    Created during planning.

  • Risk register

    Why it's wrong here

    Created during planning.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.