PK0-005 Project Management Concepts Practice Question
Which THREE of the following are responsibilities of a project manager? (Select THREE).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Communicating project status to stakeholders
The project manager plans, executes, and controls the project, manages the team, and communicates with stakeholders. The sponsor provides resources, and the steering committee provides governance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Resolving escalated issues beyond PM authority
Why it's wrong here
That is the sponsor's role.
- ✓
Communicating project status to stakeholders
Why this is correct
PM communicates progress.
- ✓
Developing the project management plan
Why this is correct
PM is responsible for planning.
- ✗
Securing project funding
Why it's wrong here
This is typically the sponsor's role.
- ✓
Managing the project team
Why this is correct
PM leads the team.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.