Which THREE of the following are responsibilities of a project manager? (Select THREE).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Communicating project status to stakeholders

The project manager plans, executes, and controls the project, manages the team, and communicates with stakeholders. The sponsor provides resources, and the steering committee provides governance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Resolving escalated issues beyond PM authority

    Why it's wrong here

    That is the sponsor's role.

  • Communicating project status to stakeholders

    Why this is correct

    PM communicates progress.

  • Developing the project management plan

    Why this is correct

    PM is responsible for planning.

  • Securing project funding

    Why it's wrong here

    This is typically the sponsor's role.

  • Managing the project team

    Why this is correct

    PM leads the team.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.