Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?

⚠ Common exam trap

PK0-005 often tests the order and purpose of closing activities — candidates pick lessons learned or archiving because they are closing tasks, but only formal acceptance obtains sponsor or customer sign-off on deliverables.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Obtaining formal acceptance

Obtaining formal acceptance is the project closing activity in which the sponsor or customer formally signs off on the deliverables, confirming they meet requirements and bringing the project to an authorized close. This typically involves a formal acceptance document, sign-off, or completion certificate. It is the activity specifically tied to gaining stakeholder approval of deliverables.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Conducting lessons learned

    Why it's wrong here

    Lessons learned capture process improvements for future projects; they do not obtain sponsor sign-off on deliverables. They are tempting because they occur during closing, but formal acceptance requires the sponsor or customer to review and sign the acceptance documentation, confirming deliverables meet requirements.

  • ✗

    Archiving project documents

    Why it's wrong here

    Archiving project documents stores records for future reference or audit; it does not obtain acceptance. It is tempting because it happens during closing, but formal acceptance is the sponsor or customer signing the acceptance form or deliverable sign-off, confirming the outputs meet requirements.

  • ✗

    Releasing resources

    Why it's wrong here

    Releasing resources returns team members and infrastructure once work concludes; it does not secure formal acceptance. It is tempting because it is a closing activity, but acceptance must precede release, with the sponsor or customer signing off that deliverables satisfy the agreed requirements.

  • ✓

    Obtaining formal acceptance

    Why this is correct

    Obtaining formal acceptance is the closing activity where the sponsor or customer signs off on the deliverables, confirming they meet requirements. This documented approval is what formally closes the project and satisfies the acceptance criterion in the stem.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.