PK0-005 Project Life Cycle Practice Question

During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Obtaining formal acceptance

Formal acceptance is documented, often through a sign-off, to confirm that deliverables meet requirements and the project is complete.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Conducting lessons learned

    Why it's wrong here

    Lessons learned can occur before final acceptance.

  • Archiving project documents

    Why it's wrong here

    Archiving is done after acceptance.

  • Releasing resources

    Why it's wrong here

    Resources are released after acceptance.

  • Obtaining formal acceptance

    Why this is correct

    Correct: Formal acceptance is a key closing activity.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.