PK0-005 Tools and Documentation Practice Question
A project manager is tracking remaining work over the course of a sprint to see if the team is on pace to complete all committed stories. Which agile artifact should the project manager use?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Burndown chart
A burndown chart shows remaining work (e.g., story points) over time in a sprint, helping visualize whether the team is on track.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Velocity chart
Why it's wrong here
Velocity shows average story points per sprint, not within a sprint.
- ✗
Burnup chart
Why it's wrong here
A burnup chart shows completed work, not remaining work.
- ✓
Burndown chart
Why this is correct
Correct – burndown tracks remaining work.
- ✗
Gantt chart
Why it's wrong here
Gantt charts are for schedule tracking, not sprint progress.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.