Courseiva
Tools and DocumentationeasyMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project manager is tracking remaining work over the course of a sprint to see if the team is on pace to complete all committed stories. Which agile artifact should the project manager use?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Burndown chart

A burndown chart shows remaining work (e.g., story points) over time in a sprint, helping visualize whether the team is on track.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Velocity chart

    Why it's wrong here

    Velocity shows average story points per sprint, not within a sprint.

  • Burnup chart

    Why it's wrong here

    A burnup chart shows completed work, not remaining work.

  • Burndown chart

    Why this is correct

    Correct – burndown tracks remaining work.

  • Gantt chart

    Why it's wrong here

    Gantt charts are for schedule tracking, not sprint progress.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.