PK0-005 Project Life Cycle Practice Question
During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Change control board
The change control board (CCB) reviews and approves change requests.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Change control board
Why this is correct
CCB is responsible for approving or rejecting changes.
- ✗
Functional manager
Why it's wrong here
Functional manager may provide resources but not approve changes.
- ✗
Project sponsor
Why it's wrong here
The sponsor may be part of CCB but not always the sole approver.
- ✗
Project manager
Why it's wrong here
The PM analyzes impact but typically does not approve; CCB does.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.