Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Change control board

The change control board (CCB) reviews and approves change requests.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Change control board

    Why this is correct

    CCB is responsible for approving or rejecting changes.

  • Functional manager

    Why it's wrong here

    Functional manager may provide resources but not approve changes.

  • Project sponsor

    Why it's wrong here

    The sponsor may be part of CCB but not always the sole approver.

  • Project manager

    Why it's wrong here

    The PM analyzes impact but typically does not approve; CCB does.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.