During a project to deploy a new enterprise resource planning (ERP) system, the project manager identifies that the vendor's implementation methodology does not align with the organization's change management process. The project manager needs to address this misalignment. What should the project manager do FIRST?

⚠ Common exam trap

The trap here is jumping to a solution or escalation before fully understanding the issue's impact, which can lead to unnecessary conflict or ineffective fixes.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Document the misalignment in the issue log and assess its impact on the project.

The project manager should first document the misalignment and assess its impact, as this is a standard issue management practice. This step provides the necessary information to evaluate options and engage stakeholders effectively. Escalating, demanding vendor changes, or altering organizational processes are premature without understanding the consequences.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Modify the organization's change management process to align with the vendor's methodology.

    Why it's wrong here

    Changing the organization's established change management process is a significant decision that could have broader impacts. The project manager should not take this step without first assessing the issue and consulting stakeholders. It may not be necessary if a compromise can be reached.

  • ✗

    Request the vendor to change its methodology to match the organization's process.

    Why it's wrong here

    Unilaterally requesting the vendor to change its methodology may be unrealistic and could strain the relationship. The project manager should first understand the implications and explore collaborative solutions. The vendor's methodology may be contractually agreed upon, so a direct demand is not the best first step.

  • ✓

    Document the misalignment in the issue log and assess its impact on the project.

    Why this is correct

    The project manager should first document the issue and analyze its potential impact on scope, schedule, and stakeholder satisfaction. This systematic approach allows for informed decision-making and helps determine the appropriate response, such as negotiating with the vendor or adjusting the change management process.

  • ✗

    Escalate the issue to the project sponsor.

    Why it's wrong here

    Escalating immediately is premature. The project manager should first assess the impact and explore possible resolutions with the vendor. Escalation is appropriate if the issue cannot be resolved at the project level, but doing so first may damage the relationship and delay resolution.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.