PK0-005 Practice Question: A project manager is reviewing the risk register…

A project manager is reviewing the risk register and sees a risk with high probability and high impact. The risk response strategy chosen is to purchase insurance. This is an example of which risk response strategy?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Transfer

Transfer involves shifting the impact of a risk to a third party, such as through insurance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Avoid

    Why it's wrong here

    Avoid eliminates the risk entirely, not transfer through insurance.

  • Accept

    Why it's wrong here

    Acceptance acknowledges the risk without proactive action; insurance is proactive transfer.

  • Transfer

    Why this is correct

    Insurance transfers financial risk to the insurance company.

  • Mitigate

    Why it's wrong here

    Mitigate reduces probability or impact, not transfers.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.