Courseiva
Tools and DocumentationeasyMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

Which document formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project charter

The project charter is the document that formally authorizes the project and gives the project manager authority.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why this is correct

    Correct – the charter authorizes the project.

  • Statement of work

    Why it's wrong here

    SOW describes the work, but does not authorize the project.

  • Project management plan

    Why it's wrong here

    The PMP describes how the project will be executed, but doesn't authorize it.

  • Business case

    Why it's wrong here

    Business case justifies the project but does not authorize it.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.