Which document formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities?

⚠ Common exam trap

PK0-005 often tests the distinction between the charter (authorizes the project) and the business case (justifies it) or the project management plan (describes execution) — candidates may pick the business case because it sounds foundational, but only the charter grants formal authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project charter

The project charter is the document that formally authorizes the project and gives the project manager authority to apply organizational resources to project activities. It is typically issued by the project sponsor or initiating authority and marks the transition from pre-project work to the formal project lifecycle. Without a charter, the project manager lacks formal authority.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project charter

    Why this is correct

    The project charter is the formal document that authorises the project's existence and grants the project manager authority to apply organisational resources. It satisfies the stem's requirement for both formal authorisation and resource-application authority, distinguishing it from plans or business cases.

  • ✗

    Statement of work

    Why it's wrong here

    A statement of work defines deliverables, scope and timelines for contracted work; it does not confer project authorisation or resource authority. It is tempting because it precedes project work in procurement contexts, but the charter is the document that formally authorises the project and empowers the project manager.

  • ✗

    Project management plan

    Why it's wrong here

    The project management plan describes how the project will be executed, monitored and controlled; it is created after authorisation, not the instrument granting it. It is tempting because it governs the project manager's approach, yet the charter is what formally recognises the project and confers authority over organisational resources.

  • ✗

    Business case

    Why it's wrong here

    A business case justifies the investment and compares options, but it grants no formal authority over organisational resources. It is tempting because it precedes and often triggers the project. A business case would be the correct artefact when the question asks what justifies funding rather than what authorises the project.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.