PK0-005 Project Life Cycle Practice Question
During project closing, which activity involves obtaining formal acceptance from the customer or sponsor that deliverables meet requirements?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Formal acceptance
Formal acceptance is obtained from the customer or sponsor during closing, often via a project acceptance form.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Lessons learned
Why it's wrong here
Lessons learned capture knowledge, not acceptance.
- ✓
Formal acceptance
Why this is correct
Formal acceptance confirms deliverables are accepted.
- ✗
Archiving project documents
Why it's wrong here
Archiving is done after acceptance.
- ✗
Final project report
Why it's wrong here
The report summarizes performance.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.