Courseiva
easyMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project team is working on a construction…

A project team is working on a construction project and is experiencing frequent change requests from the client. The project manager wants to ensure that all changes are properly evaluated and approved before implementation. Which project management process should the project manager implement?

⚠ Common exam trap

Watch out — candidates often confuse 'Monitor and Control Project Work' (which involves tracking and reporting performance) with the formal change control process, but the key distinction is that Perform Integrated Change Control is the specific process for evaluating and approving changes, not just monitoring them.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform Integrated Change Control

Perform Integrated Change Control (D) is the correct process because it is the formal process within project management that ensures all change requests are reviewed, evaluated for impact on scope, schedule, cost, and quality, and approved or rejected before implementation. This process integrates the change across all knowledge areas and requires documented approval, which directly addresses the project manager's need to evaluate and approve changes before they are implemented.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Monitor and Control Project Work

    Why it's wrong here

    This process tracks, reviews, and reports overall progress.

  • Close Project or Phase

    Why it's wrong here

    This process finalizes all activities across all process groups.

  • Direct and Manage Project Work

    Why it's wrong here

    This process executes the work defined in the project management plan.

  • Perform Integrated Change Control

    Why this is correct

    This process reviews all change requests and manages changes to deliverables and project documents.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.