easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project team is working on a construction…
A project team is working on a construction project and is experiencing frequent change requests from the client. The project manager wants to ensure that all changes are properly evaluated and approved before implementation. Which project management process should the project manager implement?
⚠ Common exam trap
Watch out — candidates often confuse 'Monitor and Control Project Work' (which involves tracking and reporting performance) with the formal change control process, but the key distinction is that Perform Integrated Change Control is the specific process for evaluating and approving changes, not just monitoring them.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Perform Integrated Change Control
Perform Integrated Change Control (D) is the correct process because it is the formal process within project management that ensures all change requests are reviewed, evaluated for impact on scope, schedule, cost, and quality, and approved or rejected before implementation. This process integrates the change across all knowledge areas and requires documented approval, which directly addresses the project manager's need to evaluate and approve changes before they are implemented.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Monitor and Control Project Work
Why it's wrong here
This process tracks, reviews, and reports overall progress.
- ✗
Close Project or Phase
Why it's wrong here
This process finalizes all activities across all process groups.
- ✗
Direct and Manage Project Work
Why it's wrong here
This process executes the work defined in the project management plan.
- ✓
Perform Integrated Change Control
Why this is correct
This process reviews all change requests and manages changes to deliverables and project documents.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.