PK0-005 Practice Question: A project team is working on a construction…

A project team is working on a construction project and is experiencing frequent change requests from the client. The project manager wants to ensure that all changes are properly evaluated and approved before implementation. Which project management process should the project manager implement?

⚠ Common exam trap

Watch out — candidates often confuse 'Monitor and Control Project Work' (which involves tracking and reporting performance) with the formal change control process, but the key distinction is that Perform Integrated Change Control is the specific process for evaluating and approving changes, not just monitoring them.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Perform Integrated Change Control

Perform Integrated Change Control (D) is the correct process because it is the formal process within project management that ensures all change requests are reviewed, evaluated for impact on scope, schedule, cost, and quality, and approved or rejected before implementation. This process integrates the change across all knowledge areas and requires documented approval, which directly addresses the project manager's need to evaluate and approve changes before they are implemented.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Monitor and Control Project Work

    Why it's wrong here

    Monitor and Control Project Work tracks and reports performance against the plan; it does not evaluate, approve or document change requests. It is correct for ongoing status measurement, forecasting and corrective action, whereas change requests require Perform Integrated Change Control.

  • ✗

    Close Project or Phase

    Why it's wrong here

    Closing a project or phase finalises deliverables and releases resources once work is complete; it cannot evaluate or approve incoming change requests during execution. It is tempting because closing formally records completed changes, and would be correct at project end to obtain final acceptance and archive change documentation.

  • ✗

    Direct and Manage Project Work

    Why it's wrong here

    Directing and managing project work executes the approved plan and produces deliverables; it implements changes already authorised, but performs no evaluation or approval of incoming requests. It is tempting because approved changes are executed here, and would be correct once the change control process has authorised a request.

  • ✓

    Perform Integrated Change Control

    Why this is correct

    Perform Integrated Change Control provides a formal review and approval gate, so every client request is evaluated for impact before implementation. It satisfies the stem's constraint that changes be properly assessed and authorised, unlike direct execution or informal tracking. This process owns the change control board and updates baselines once approved.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.