Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

In which type of organizational structure does the project manager have the least authority?

⚠ Common exam trap

PK0-005 often tests the continuum of project manager authority across organizational structures, and candidates may incorrectly assume matrix structures give less authority than functional.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Functional

In a functional organizational structure, the project manager has the least authority because team members report to functional managers, and the project manager acts more as a coordinator. The functional manager controls resources and priorities, leaving the project manager with limited power.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Functional

    Why this is correct

    In a functional organisation, authority rests with the functional manager, who controls resources, budgets and team assignments. The project manager coordinates across departments with little formal power, often acting as a coordinator or expediter rather than a true leader. This directly satisfies the stem's constraint of least project manager authority.

  • ✗

    Projectized

    Why it's wrong here

    Project managers have full authority in projectized structures.

  • ✗

    Balanced matrix

    Why it's wrong here

    A balanced matrix splits authority evenly between the functional manager and project manager, so the project manager retains shared, not least, authority. It is tempting because matrix structures blur reporting lines, yet balanced matrices still assign the project manager meaningful control over resources and scheduling decisions.

  • ✗

    Strong matrix

    Why it's wrong here

    A strong matrix grants the project manager significant authority over resources and budget, second only to a projectised structure, so it cannot be the least-authority answer. It is tempting because matrix structures do dilute functional control, but strong matrices deliberately concentrate power with the project manager rather than removing it.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.