Courseiva
mediumMultiple SelectObjective-mapped

PK0-005 Practice Question: Which THREE of the following are examples of…

Which THREE of the following are examples of project constraints?

⚠ Common exam trap

CompTIA often tests the distinction between constraints (scope, time, cost) and other project management elements like communication or risk, which are processes or uncertainties, not fixed limitations.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Scope

Scope is a classic project constraint because it defines the boundaries of what the project will deliver. Any change to scope directly impacts time and cost, forming the core of the triple constraint model. In project management, scope must be clearly defined and controlled to prevent scope creep, which can derail project objectives.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scope

    Why this is correct

    Classic constraint.

  • Time

    Why this is correct

    Classic constraint.

  • Communication

    Why it's wrong here

    Not a core constraint.

  • Cost

    Why this is correct

    Classic constraint.

  • Risk

    Why it's wrong here

    Risk is an uncertain event.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.