Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Decomposition

Decomposition is the process of subdividing project deliverables into smaller work packages.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Decomposition

    Why this is correct

    Correct: decomposition breaks down deliverables.

  • Bottom-up estimating

    Why it's wrong here

    Bottom-up is a cost estimation technique.

  • Precedence diagramming

    Why it's wrong here

    Precedence diagramming is used for network diagrams.

  • Rolling wave planning

    Why it's wrong here

    Rolling wave is a progressive elaboration technique.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.