Courseiva
Project Life CyclehardMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project has earned value (EV) of $120,000, planned value (PV) of $100,000, and actual cost (AC) of $110,000. What is the cost performance index (CPI)?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

1.09

CPI = EV / AC = $120,000 / $110,000 = 1.09.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 1.09

    Why this is correct

    CPI = EV/AC = 1.09.

  • 0.91

    Why it's wrong here

    That would be AC/EV.

  • 1.10

    Why it's wrong here

    That is not the correct calculation.

  • 1.20

    Why it's wrong here

    That would be EV/PV.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.