Practise CompTIA Project+ PK0-005 Project Life Cycle practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

161 questions38 easy80 medium43 hard

Focused practice

Practice Project Life Cycle questions

Scored sessions drawing only from this domain — pick a length below.

Start 20-question practice test →

What this domain covers

What to know about Project Life Cycle

Project Life Cycle questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common Project Life Cycle exam traps

  • Answering from memory before reading the full scenario.
  • Missing a constraint such as cost, availability, security, scope or command context.
  • Choosing a broad answer when the question asks for the most specific fix.
  • Ignoring why the wrong options are tempting.

Question index

All Project Life Cycle questions (161)

Click any question to see the full explanation, or start a practice session above.

1

In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?

Hard
2

During project execution, the project manager notices that the team is struggling with communication, and key stakeholders are not receiving timely updates. Which THREE documents should the project manager review to improve the situation? (Select THREE).

Hard
3

A project manager is estimating the cost of a software development project. Using data from a similar past project, she adjusts for size and complexity. Which estimation technique is she using?

Medium
4

During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?

Hard
5

Which TWO documents are typically created during the project initiating phase?

Easy
6

A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)

Medium
7

Which of the following is the primary purpose of a feasibility study during the initiating phase?

Medium
8

A project manager is analyzing the critical path of a network diagram. Which TWO statements about the critical path are true?

Medium
9

A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?

Medium
10

A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?

Medium
11

A project manager is preparing a request for proposal (RFP) for a vendor to provide specialized equipment. Which THREE items should be included in the RFP?

Medium
12

A change request is submitted to add a new feature to a project. What is the first step the project manager should take?

Medium
13

A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?

Easy
14

A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?

Medium
15

During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?

Medium
16

A project manager identifies a key stakeholder who has high interest in the project but low power to influence decisions. In the power/interest grid, where should this stakeholder be placed?

Easy
17

Which contract type places the most cost risk on the seller?

Medium
18

A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?

Medium
19

A project manager is estimating the cost of a software development project. She uses the actual cost of a similar past project and adjusts it for known differences in size and complexity. Which cost estimation technique is she using?

Medium
20

A project manager uses a power/interest grid to categorize stakeholders. Stakeholders with high power and low interest should be managed using which approach?

Medium
21

A project manager is conducting a lessons learned session at the end of a project. Which TWO activities are typically performed during project closure? (Select two.)

Medium
22

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. Which TWO statements are true regarding the project's performance? (Choose two.)

Hard
23

Which document is used to formally accept the project deliverables and signify project closure?

Easy
24

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?

Hard
25

In which Tuckman stage do team members begin to resolve their differences, establish norms, and develop closer relationships?

Easy
26

During which phase of the project life cycle is the project charter created and stakeholders initially identified?

Easy
27

A project manager is reviewing the project schedule. Activity A has an early start (ES) of day 1 and an early finish (EF) of day 5. Activity B has an ES of day 6 and an EF of day 10. Activity C has a duration of 2 days and depends on both A and B. What is the total float of Activity B if the project must be completed by day 12?

Hard
28

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.8. What does this indicate about the project?

Hard
29

A project manager is leading a cross-functional team that is working together for the first time. The team members are polite but hesitant to share ideas. According to Tuckman's stages of group development, which stage is the team currently in?

Easy
30

A project manager identifies a risk that could cause a $50,000 loss with a 20% probability. What is the expected monetary value (EMV) of this risk?

Hard
31

In a network diagram using PDM, activity B can start only after activity A has finished. Which dependency type does this represent?

Medium
32

A project manager is assigning stakeholders to quadrants on a power/interest grid. Which stakeholders require the most active management?

Medium
33

During project closure, which three activities should be performed? (Select THREE)

Hard
34

In the stakeholder power/interest grid, stakeholders with high power and low interest should be managed using which strategy?

Easy
35

During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)

Medium
36

A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?

Medium
37

A project manager is developing a network diagram for a software rollout. Activity D (3 days) can start only after Activity C (2 days) finishes, and Activity E (4 days) can start when Activity C starts. Activities D and E must both finish before Activity F (1 day) begins. What type of dependency exists between Activity C and Activity E?

Medium
38

In which project management process group is the project charter formally approved, giving the project manager authority to allocate resources?

Medium
39

During which project phase is the project charter created?

Easy
40

In a precedence diagramming method (PDM) network, a successor activity cannot start until its predecessor activity has started. Which type of dependency does this represent?

Medium
41

A project manager is updating the risk register and plans to respond to a high-priority risk. Which THREE are examples of proactive risk response strategies?

Medium
42

A project is in the monitoring and controlling phase. The project manager is reviewing the earned value metrics: EV = $50,000, PV = $60,000, AC = $55,000. Which of the following statements is correct?

Hard
43

A project has earned value (EV) of $50,000, planned value (PV) of $60,000, and actual cost (AC) of $55,000. What is the cost performance index (CPI)?

Hard
44

In a network diagram, Activity A has a duration of 5 days, Activity B has 3 days, and Activity C has 4 days. Activity A and B can start simultaneously, but Activity C cannot start until both A and B are complete. What is the critical path duration?

Hard
45

Which document formally authorizes the project and assigns the project manager?

Easy
46

A project manager has identified a risk that could cause a $50,000 loss with a 20% probability. What is the Expected Monetary Value (EMV) of this risk?

Easy
47

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

Medium
48

During project execution, a vendor is hired to provide specialized services. The contract is structured so that the vendor is paid for all allowable costs plus a fixed fee. Which type of contract is this?

Hard
49

A project manager is creating a document that formally authorizes the project and assigns the project manager. This document includes the business case, high-level scope, and budget constraints. What is this document called?

Easy
50

A project has three activities on the critical path: A (5 days), B (10 days), C (5 days). Activity D (8 days) has a total float of 3 days. If activity B is delayed by 2 days, what is the new project duration?

Hard
51

A project manager is analyzing the network diagram and identifies that Activity X has a late start (LS) of day 10 and an early start (ES) of day 8. Which TWO statements are true about Activity X? (Select two.)

Hard
52

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000, and the actual cost (AC) is $150,000. What is the estimate to complete (ETC) assuming the project will continue to perform at the same cost efficiency?

Hard
53

In a network diagram, if Activity B cannot start until Activity A is complete, what type of dependency is this?

Medium
54

A project has three activities: Activity A (5 days), Activity B (7 days), Activity C (4 days). Activity B depends on A. Activity C depends on B. What is the total float for Activity B?

Hard
55

Which risk response strategy involves taking action to reduce the probability or impact of a risk?

Easy
56

During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?

Medium
57

During project planning, the project manager decomposes the project scope into smaller, more manageable components. What is the resulting document called?

Medium
58

A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)

Medium
59

Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?

Easy
60

During the planning phase, which three documents are typically created? (Select THREE.)

Medium
61

A project manager is reviewing the procurement process. Which document is used to invite vendors to submit a proposal for a project?

Hard
62

A project team is decomposing the project scope into work packages. Which of the following best describes the purpose of a Work Breakdown Structure (WBS)?

Hard
63

A project manager is closing a project. Which TWO activities are typically performed during the closing phase?

Medium
64

A project manager needs to communicate project progress to stakeholders who have low power and high interest. Which of the following is the most appropriate communication method?

Medium
65

A project manager is evaluating the cost performance of a project. Which TWO earned value metrics should be used to determine if the project is over budget?

Hard
66

A project manager is performing quantitative risk analysis. Which THREE of the following techniques are commonly used? (Select three.)

Hard
67

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

Hard
68

During which stage of Tuckman's team development model do team members begin to resolve conflicts and establish norms?

Medium
69

A project manager is monitoring project performance. Which TWO earned value metrics are used to assess cost efficiency?

Medium
70

A project is in the Executing phase. The project manager needs to ensure effective communication with stakeholders. Which THREE elements should be included in the communications management plan? (Select THREE.)

Hard
71

A project manager is estimating activity durations for a construction project. She uses a parametric estimate based on 100 square meters per day. If the total area is 500 square meters, the estimated duration is 5 days. Which THREE statements are true about parametric estimation?

Medium
72

During which project phase is the project charter created and the project manager officially assigned?

Easy
73

Which type of contract places the greatest cost risk on the seller?

Medium
74

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

Hard
75

Which of the following is an example of a risk response strategy to avoid a risk?

Easy
76

During which project phase is the project charter created and the project manager formally assigned?

Easy
77

During which project phase is the project charter typically created and approved?

Easy
78

According to Tuckman's model, during which stage do team members begin to resolve conflicts and establish norms?

Medium
79

A project manager is using a risk probability and impact matrix. A risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Medium
80

During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?

Medium
81

During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?

Hard
82

Which cost estimation technique uses historical data from similar projects to estimate the cost of the current project?

Easy
83

A project team is in the storming stage of Tuckman's model. Which of the following behaviors is most likely to be observed?

Easy
84

Which of the following is a common response strategy for negative risks (threats) that involves reducing the probability or impact of the risk?

Easy
85

A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?

Medium
86

Which contract type places the most cost risk on the seller?

Easy
87

During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?

Medium
88

During project execution, the project team is experiencing conflicts and questioning the project manager's authority. According to Tuckman's model, which stage is the team in?

Hard
89

A project manager has identified a stakeholder with high power and high interest. According to the power/interest grid, how should this stakeholder be managed?

Medium
90

During the planning phase, a project manager is creating the WBS. Which of the following best describes the process of breaking down deliverables into smaller, more manageable components?

Hard
91

A project manager identifies a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Medium
92

A project has the following activities and dependencies: A (5 days), B (3 days, after A), C (4 days, after A), D (2 days, after B), E (6 days, after C), F (1 day, after D and E). What is the total float of activity C?

Hard
93

A project manager is estimating costs for a new software development project. The company has completed three similar projects in the past. Which cost estimation technique is most appropriate in this scenario?

Medium
94

A project manager is developing a communication plan. Which of the following should be determined first?

Medium
95

During the executing phase, a vendor delivers a product that does not meet the specifications outlined in the SOW. Which document should the project manager reference first to address this issue?

Hard
96

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)

Medium
97

During project closing, which THREE activities should be performed?

Medium
98

A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?

Hard
99

Which document contains all identified risks, their probability and impact, and planned response strategies?

Easy
100

A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)

Hard
101

A project manager receives a change request from a stakeholder. What is the first step the project manager should take?

Easy
102

A project manager needs to communicate the project's progress to stakeholders with high power and low interest. According to the power/interest grid, which communication approach is most appropriate?

Medium
103

A project manager is calculating the cost performance index (CPI) for a project. The earned value (EV) is $50,000 and the actual cost (AC) is $60,000. What does the CPI indicate? (Select TWO correct statements.)

Medium
104

A project manager is creating a WBS. Which two best practices should be followed? (Select TWO)

Medium
105

A project has an EV of $40,000, PV of $50,000, and AC of $45,000. What is the cost performance index (CPI)?

Medium
106

A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?

Medium
107

In a power/interest grid, stakeholders with high power and low interest should be managed with which approach?

Easy
108

A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?

Medium
109

A project has three activities on the critical path. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. What is the total float for any activity on the critical path?

Medium
110

A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?

Easy
111

During risk management, a team identifies a risk with a 20% probability of occurrence and a potential cost impact of $50,000. What is the Expected Monetary Value (EMV) of this risk?

Medium
112

A project has earned value (EV) of $120,000, planned value (PV) of $100,000, and actual cost (AC) of $110,000. What is the cost performance index (CPI)?

Hard
113

During project closing, which of the following is the primary purpose of the lessons learned document?

Medium
114

A project manager is estimating the cost of a new software development project. The project is similar to a previous project that cost $500,000. The PM adjusts for size and complexity and estimates the new project will cost $600,000. Which estimation technique is being used?

Medium
115

Which of the following is a key input to the change control process when a change request is submitted?

Medium
116

A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?

Hard
117

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. What is the cost performance index (CPI) and what does it indicate?

Hard
118

A project manager is developing the project charter. Which of the following should be included as a key element in the charter to define the project's boundaries?

Medium
119

A project manager is calculating the critical path. The network diagram shows two paths: Path A: A(3 days) → B(4 days) → C(2 days) = 9 days; Path B: D(5 days) → E(1 day) → F(3 days) = 9 days. Both have total float of zero. What is the total float for an activity on Path A?

Hard
120

A project has a critical path duration of 45 days. Activity X on the critical path has an optimistic duration of 5 days, a pessimistic duration of 13 days, and a most likely duration of 8 days. What is the expected duration of activity X using PERT?

Hard
121

In a network diagram, Activity B has a duration of 5 days. Its predecessor is Activity A (duration 3 days) with a finish-to-start relationship. Activity C (duration 4 days) has a start-to-start relationship with Activity B with a 2-day lag. What is the earliest day Activity C can start?

Hard
122

A project has a budget at completion (BAC) of $200,000. After two months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. The CPI is 0.89. Which THREE statements are correct regarding cost performance and forecasting?

Hard
123

A project manager is evaluating a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Medium
124

A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?

Medium
125

During project executing, the team is developing a communication plan. Which THREE factors should the project manager consider when determining the communication needs of stakeholders?

Medium
126

During project closing, which TWO activities are typically performed?

Easy
127

During project closing, which activity involves obtaining formal acceptance from the customer or sponsor that deliverables meet requirements?

Medium
128

Which project management process group involves obtaining formal acceptance of the project deliverables and archiving project documents?

Easy
129

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

Medium
130

A project manager identifies a risk that a key team member might leave during the project. To reduce the impact, she cross-trains other team members. Which risk response strategy is being applied?

Medium
131

In earned value management, the project has an EV of $50,000, PV of $60,000, and AC of $55,000. What is the cost variance (CV)?

Medium
132

A project manager is assigning resources to activities. Activity X requires a specialized skill that is only available from a contractor. The project manager decides to hire the contractor. Which TWO documents are most likely to be used to define the work and terms for this contractor? (Select TWO).

Hard
133

A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)

Medium
134

A project team is in the Performing stage of Tuckman's model. Which TWO behaviors are characteristic of this stage?

Easy
135

A project manager is decomposing the project scope into smaller components. Which output is produced?

Medium
136

A project manager is in the process of developing the project charter. Which of the following would be included in the project charter?

Easy
137

During project execution, a team member proposes a change that will affect the scope baseline. What is the first step the project manager should take?

Hard
138

A project has a budget at completion (BAC) of $200,000, earned value (EV) of $120,000, and actual cost (AC) of $130,000. What is the estimate at completion (EAC) if the cost performance is expected to continue?

Hard
139

In a fixed-price contract, which party bears the risk of cost overruns?

Easy
140

During the executing phase, a project manager observes that team members are starting to collaborate and share ideas openly. According to Tuckman's stages of team development, which stage is the team likely in?

Medium
141

A project manager is estimating the cost of a new software development project. They use historical data from a similar project to derive the cost per function point and multiply it by the expected number of function points. Which estimation technique is being used?

Medium
142

A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?

Easy
143

A project is in the Monitoring and Controlling phase. A change request has been submitted to add a new feature. The change control board (CCB) has approved the change. Which THREE actions should the project manager take next?

Hard
144

A project team is estimating costs for a new software development project. They use data from a similar previous project and adjust for size differences. Which estimating technique is being used?

Medium
145

A project manager is identifying stakeholders for a new product launch. She uses a power/interest grid to categorize stakeholders. For which ONE quadrant should the project manager apply the strategy of 'Manage Closely'?

Medium
146

Which cost estimation technique uses historical data from similar projects to estimate the current project?

Easy
147

What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?

Easy
148

A project manager is estimating the cost of a new software development project. Since the project is similar to a previous one, the manager uses the cost of the previous project as a basis, adjusting for known differences. Which cost estimation technique is being used?

Medium
149

During project planning, the team creates a hierarchical decomposition of the total scope of work to be carried out by the project team. Each descending level represents an increasingly detailed definition of the project work. What is this called?

Medium
150

A project team is in the process of obtaining seller responses, evaluating proposals, and awarding a contract. Which procurement document is used to formally request a proposal from potential sellers?

Medium
151

A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?

Medium
152

During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?

Medium
153

A project manager is closing a project. Which THREE activities are part of the project closure process? (Select THREE).

Medium
154

During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?

Easy
155

A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?

Medium
156

A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?

Medium
157

Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)

Easy
158

A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?

Easy
159

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

Easy
160

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

Medium
161

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

Hard

Frequently asked questions

What does the Project Life Cycle domain cover on the PK0-005 exam?
Project Life Cycle questions test whether you can apply the concept in context, not just recognise a definition.
How many questions are in this domain?
This page lists all 161 Project Life Cycle questions in the PK0-005 question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
What is the best way to practise this domain?
Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
Can I practise only Project Life Cycle questions?
Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.