Question 349 of 500
Project Management ConceptshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is to facilitate a meeting to prioritize requirements and reach consensus. This is correct because stakeholder alignment during project initiation is the project manager’s primary responsibility, and the core technical concept here is that conflicting objectives—like maximizing functionality versus minimizing cost—must be resolved through facilitated negotiation before the charter is finalized. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of the initiation phase’s key deliverable: a charter that reflects agreed-upon goals, not just a draft. A common trap is choosing to escalate to the sponsor or simply document the disagreement, but the best approach is proactive facilitation to achieve consensus, as the project manager acts as a neutral bridge. Remember the memory tip: “Facilitate first, escalate last”—always guide stakeholders to prioritize requirements together before seeking higher authority.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A large government project is in the initiation phase. The project charter has been drafted, but there is disagreement among key stakeholders about the project's objectives. Some stakeholders want to maximize functionality, while others want to minimize cost. The project manager must lead the effort to resolve this. Which of the following is the BEST approach?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "best"

    Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

  • Clue: "minimum / minimize"

    Why it matters: Asks for the least resource use — fewest addresses, smallest subnet, lowest overhead. Eliminate over-provisioned options even if they would technically work.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a meeting to prioritize requirements and reach consensus.

Option B is correct because the project manager's role during the initiation phase is to align stakeholders on project objectives. Facilitating a meeting to prioritize requirements and reach consensus directly addresses the disagreement between maximizing functionality and minimizing cost, ensuring the project charter reflects agreed-upon goals before proceeding.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Proceed with the charter as written, as it has been signed by the sponsor.

    Why it's wrong here

    The charter is drafted but not finalized if there is disagreement.

  • Facilitate a meeting to prioritize requirements and reach consensus.

    Why this is correct

    Facilitation helps stakeholders find common ground.

    Clue confirmation

    The clue words "best", "minimum / minimize" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Conduct a cost-benefit analysis and present the results to stakeholders.

    Why it's wrong here

    This provides information but does not directly resolve the disagreement.

  • Divide the project into phases, starting with a small pilot to gather data.

    Why it's wrong here

    Phasing is a strategy but does not resolve the initial conflict.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the misconception that a signed charter is final and cannot be revisited, but the trap here is that stakeholder alignment is a prerequisite for a valid charter, not a post-signature assumption.

Detailed technical explanation

How to think about this question

In project management, the initiation phase requires a clear project charter that defines scope, objectives, and constraints. Disagreement on objectives often stems from differing stakeholder priorities (e.g., functionality vs. cost), which can be resolved through techniques like MoSCoW prioritization (Must have, Should have, Could have, Won't have) or multi-voting. This ensures the charter is a binding agreement that guides all subsequent planning and execution phases.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Facilitate a meeting to prioritize requirements and reach consensus. — Option B is correct because the project manager's role during the initiation phase is to align stakeholders on project objectives. Facilitating a meeting to prioritize requirements and reach consensus directly addresses the disagreement between maximizing functionality and minimizing cost, ensuring the project charter reflects agreed-upon goals before proceeding.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "best", "minimum / minimize". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. You are a project manager for a marketing campaign project. The project has just been initiated, and you are working with the sponsor to identify key stakeholders. The project involves multiple departments: marketing, sales, IT, and legal. One of the stakeholders from sales has expressed strong opposition to the project, claiming it will redirect resources away from ongoing sales initiatives. The project sponsor is concerned this stakeholder might try to block the project. What is the first step you should take to manage this situation?

easy
  • A.Meet with the sales stakeholder to understand their concerns and address them.
  • B.Update the stakeholder register and issue log, then proceed with the project.
  • C.Ask the sales department manager to replace the stakeholder.
  • D.Inform the sponsor that the stakeholder will be removed from the project.

Why A: Option A is correct because the first step in managing stakeholder opposition is to engage directly with the stakeholder to understand their concerns. This aligns with the PMI's stakeholder engagement best practices, which emphasize early communication and issue identification before escalating or documenting. By meeting with the sales stakeholder, the project manager can gather specific details about resource conflicts and work collaboratively to find a resolution, which is critical in the initiation phase of a marketing campaign project.

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.