Courseiva
Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is estimating the cost of a new software development project. Since the project is similar to a previous one, the manager uses the cost of the previous project as a basis, adjusting for known differences. Which cost estimation technique is being used?

⚠ Common exam trap

PK0-005 often tests the distinction between analogous and parametric estimation — candidates see 'previous project' and 'adjusting' and may overthink it into parametric, but the key signal is a single comparable project, not a rate-based formula.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Analogous estimation

Analogous estimation uses historical data from a similar past project as the basis for estimating the current project, adjusting for known differences. The scenario explicitly describes using a previous project's cost as a reference point, which is the textbook definition of analogous (top-down) estimating.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Parametric estimation

    Why it's wrong here

    Parametric estimation multiplies unit rates by quantities via a statistical model, such as cost per line of code. It needs measurable drivers, not a single analogous project; the stem describes adjusting one prior project's actual cost, which is analogy.

  • ✗

    Bottom-up estimation

    Why it's wrong here

    Bottom-up estimation sums individual work-package estimates into a total, requiring detailed decomposition of every component. It is correct for well-defined scopes needing high accuracy, but the stem uses one whole previous project as the baseline, which is analogy.

  • ✓

    Analogous estimation

    Why this is correct

    Analogous estimation uses historical data from a comparable past project as the basis, then adjusts for known differences. This top-down technique suits the scenario because the new project closely resembles the previous one, making prior cost a reliable anchor.

  • ✗

    Three-point estimation

    Why it's wrong here

    Three-point estimation averages optimistic, most likely and pessimistic figures using a weighted formula, which requires per-activity ranges rather than a single historical total. It suits risk-heavy tasks with uncertain durations, not analogy-based scaling of one comparable past project.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.