PK0-005 Practice Question: During project execution, a stakeholder requests…
During project execution, a stakeholder requests an additional feature. The project manager documents the request and evaluates its impact on the triple constraint. Which process is being performed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Integrated change control
Integrated change control evaluates change requests against constraints and manages approval.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk management
Why it's wrong here
Risk management handles uncertainties, not change requests.
- ✗
Configuration management
Why it's wrong here
Configuration management controls product versions, not change evaluation.
- ✗
Scope verification
Why it's wrong here
Scope verification is formal acceptance of deliverables.
- ✓
Integrated change control
Why this is correct
Correct process for evaluating changes.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.