- A
Add the feature to the project plan and adjust the schedule accordingly.
Why wrong: Adding the feature without formal analysis bypasses change control.
- B
Approve the change and inform the team to start working on it.
Why wrong: The PM does not have unilateral authority to approve changes without stakeholder input.
- C
Refuse the request because the scope was already baselined.
Why wrong: Refusing without analysis may not be appropriate; changes can be accepted after evaluation.
- D
Initiate a change request to assess the impact on cost, schedule, and resources.
This follows proper change management procedures.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is leading a software development project. The team has completed the design phase and is about to start coding. The project sponsor asks the project manager to add a new feature that was not in the original scope. What should the project manager do first?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Initiate a change request to assess the impact on cost, schedule, and resources.
Option D is correct because the project manager must first initiate a formal change request to assess the impact of the new feature on cost, schedule, and resources before any action is taken. This aligns with the PMI's integrated change control process, which requires evaluating trade-offs in a software development context where code dependencies and integration points can be affected. Adding features without analysis risks scope creep, budget overruns, and missed deadlines.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Add the feature to the project plan and adjust the schedule accordingly.
Why it's wrong here
Adding the feature without formal analysis bypasses change control.
- ✗
Approve the change and inform the team to start working on it.
Why it's wrong here
The PM does not have unilateral authority to approve changes without stakeholder input.
- ✗
Refuse the request because the scope was already baselined.
Why it's wrong here
Refusing without analysis may not be appropriate; changes can be accepted after evaluation.
- ✓
Initiate a change request to assess the impact on cost, schedule, and resources.
Why this is correct
This follows proper change management procedures.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may assume the project manager has authority to approve changes directly, but the PMI framework requires a formal change request and impact analysis first, even for sponsor requests.
Detailed technical explanation
How to think about this question
In software development projects, a change request triggers a formal impact analysis that considers not only cost and schedule but also technical debt, regression risks, and integration testing overhead. For example, adding a feature mid-cycle may require refactoring existing code modules, which can introduce bugs and delay subsequent sprints. The project manager must document the change in a change log and obtain sign-off from the change control board (CCB) before any coding begins.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Initiate a change request to assess the impact on cost, schedule, and resources. — Option D is correct because the project manager must first initiate a formal change request to assess the impact of the new feature on cost, schedule, and resources before any action is taken. This aligns with the PMI's integrated change control process, which requires evaluating trade-offs in a software development context where code dependencies and integration points can be affected. Adding features without analysis risks scope creep, budget overruns, and missed deadlines.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.