Question 276 of 500
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is leading a software development project. The team has completed the design phase and is about to start coding. The project sponsor asks the project manager to add a new feature that was not in the original scope. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiate a change request to assess the impact on cost, schedule, and resources.

Option D is correct because the project manager must first initiate a formal change request to assess the impact of the new feature on cost, schedule, and resources before any action is taken. This aligns with the PMI's integrated change control process, which requires evaluating trade-offs in a software development context where code dependencies and integration points can be affected. Adding features without analysis risks scope creep, budget overruns, and missed deadlines.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add the feature to the project plan and adjust the schedule accordingly.

    Why it's wrong here

    Adding the feature without formal analysis bypasses change control.

  • Approve the change and inform the team to start working on it.

    Why it's wrong here

    The PM does not have unilateral authority to approve changes without stakeholder input.

  • Refuse the request because the scope was already baselined.

    Why it's wrong here

    Refusing without analysis may not be appropriate; changes can be accepted after evaluation.

  • Initiate a change request to assess the impact on cost, schedule, and resources.

    Why this is correct

    This follows proper change management procedures.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may assume the project manager has authority to approve changes directly, but the PMI framework requires a formal change request and impact analysis first, even for sponsor requests.

Detailed technical explanation

How to think about this question

In software development projects, a change request triggers a formal impact analysis that considers not only cost and schedule but also technical debt, regression risks, and integration testing overhead. For example, adding a feature mid-cycle may require refactoring existing code modules, which can introduce bugs and delay subsequent sprints. The project manager must document the change in a change log and obtain sign-off from the change control board (CCB) before any coding begins.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Initiate a change request to assess the impact on cost, schedule, and resources. — Option D is correct because the project manager must first initiate a formal change request to assess the impact of the new feature on cost, schedule, and resources before any action is taken. This aligns with the PMI's integrated change control process, which requires evaluating trade-offs in a software development context where code dependencies and integration points can be affected. Adding features without analysis risks scope creep, budget overruns, and missed deadlines.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.