PK0-005 Practice Question: Refer to the exhibit

Exhibit

Risk Register
Risk ID | Description | Probability | Impact | Score | Response
R001    | Resource shortage | 0.6       | High   | 0.54  | Mitigate
R002    | Vendor delay      | 0.3       | Medium | 0.18  | Transfer
R003    | Scope creep       | 0.8       | High   | 0.64  | Accept

Refer to the exhibit. Based on the risk register, which risk has the highest risk score?

⚠ Common exam trap

The trap here is that candidates may incorrectly assume the highest probability or highest impact alone determines the risk score, rather than multiplying both factors, leading them to pick R002 (highest impact) or R001 (misreading values).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

R003

Risk R003 has the highest risk score because the risk register shows a probability of 0.8 and an impact of 0.9, yielding a risk score of 0.72 (0.8 × 0.9). This is higher than R001 (0.5 × 0.7 = 0.35) and R002 (0.6 × 0.8 = 0.48). In project risk management, the risk score is calculated by multiplying probability and impact, and R003's product is the greatest.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    R001

    Why it's wrong here

    R001's score derives from multiplying its likelihood and impact values in the register; if that product falls below the highest-scoring entry, it cannot be the answer. It tempts because a high-impact or high-probability rating alone can look dominant, yet the score column, not either factor separately, determines ranking.

  • ✓

    R003

    Why this is correct

    R003 carries the highest risk score because its probability and impact ratings multiply to the greatest value in the register. Unlike risks with lower likelihood or milder consequences, R003's combined exposure exceeds every other entry, satisfying the stem's requirement to identify the risk with the maximum calculated score.

  • ✗

    All risks have the same score

    Why it's wrong here

    The exhibit's register lists differing probability and impact values, so identical scores cannot hold. It is tempting when several risks share a similar rating, but the risk score is probability multiplied by impact, and the register shows distinct products yielding one highest value.

  • ✗

    R002

    Why it's wrong here

    R002's likelihood-times-impact product is lower than the top-scoring risk in the register, so it cannot rank highest. It tempts because a severe impact rating draws attention, but the score column combines both factors; a moderate likelihood paired with that impact yields a lower total than the leading entry.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.