Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Parametric estimation Practice Question

A project manager is estimating the cost of a new software development project. They use historical data from a similar project to derive the cost per function point and multiply it by the expected number of function points. Which estimation technique is being used?

⚠ Common exam trap

Candidates often confuse analogous and parametric because both use historical data. The key difference is that parametric uses a mathematical model with scalability (cost per unit), whereas analogous relies on overall similarity.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Parametric estimation

Parametric estimation uses a statistical relationship between historical data and other variables (e.g., cost per function point) to calculate an estimate. In this scenario, the project manager derives a cost per function point from a similar project and multiplies it by the expected number of function points. This is a classic example of parametric estimation because it applies a unit rate to a quantity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Bottom-up estimation

    Why it's wrong here

    Bottom-up estimation involves estimating individual components and summing them; it does not use a unit rate from historical data.

  • Three-point estimation

    Why it's wrong here

    Three-point estimation uses optimistic, pessimistic, and most likely estimates, not a single historical rate.

  • Parametric estimation

    Why this is correct

    Parametric estimation uses a mathematical model with a unit rate (cost per function point) scaled by quantity, exactly matching the description.

  • Analogous estimation

    Why it's wrong here

    Analogous estimation uses historical data from similar projects but typically applies the total cost of a similar project as a basis, without a per-unit scaling factor.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.