In a network diagram, Activity B has a duration of 5 days. Its predecessor is Activity A (duration 3 days) with a finish-to-start relationship. Activity C (duration 4 days) has a start-to-start relationship with Activity B with a 2-day lag. What is the earliest day Activity C can start?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Day 6

Activity A finishes at day 3. Activity B starts at day 4 (FS+1? Actually FS means B starts after A finishes, so B starts day 4). With SS+2 lag, C can start 2 days after B starts, i.e., day 6.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Day 6

    Why this is correct

    Correct: A finishes day 3, B starts day 4, C starts 2 days after B start = day 6.

  • Day 5

    Why it's wrong here

    Incorrect calculation.

  • Day 7

    Why it's wrong here

    Incorrect.

  • Day 8

    Why it's wrong here

    Incorrect.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.