PK0-005 Project Life Cycle Practice Question
During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk description
Risk register includes risk description, probability and impact assessment, and response plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk description
Why this is correct
A description of the risk is included.
- ✓
Probability and impact assessment
Why this is correct
Qualitative assessment is standard.
- ✗
Actual cost of the project
Why it's wrong here
Actual cost is tracked in monitoring, not in risk register.
- ✓
Risk response plan
Why this is correct
Planned responses are documented.
- ✗
Team member assignments
Why it's wrong here
Assignments are in the resource management plan, not risk register.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.