Courseiva
Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk description

Risk register includes risk description, probability and impact assessment, and response plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk description

    Why this is correct

    A description of the risk is included.

  • Probability and impact assessment

    Why this is correct

    Qualitative assessment is standard.

  • Actual cost of the project

    Why it's wrong here

    Actual cost is tracked in monitoring, not in risk register.

  • Risk response plan

    Why this is correct

    Planned responses are documented.

  • Team member assignments

    Why it's wrong here

    Assignments are in the resource management plan, not risk register.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.