A project manager is leading a team to develop a new mobile application. The project has a fixed budget and a strict deadline. During the execution phase, the stakeholder requests additional features that were not originally planned. Which project constraint is most directly affected by this request?
Trap 1: Quality
Quality is not the primary constraint; scope change is the direct issue.
Trap 2: Schedule
Schedule may be affected, but the direct impact is scope increase.
Trap 3: Cost
Cost may be affected, but the primary immediate impact is on scope.
- A
Quality
Why wrong: Quality is not the primary constraint; scope change is the direct issue.
- B
Scope
Uncontrolled changes to requirements are scope creep, directly affecting scope.
- C
Schedule
Why wrong: Schedule may be affected, but the direct impact is scope increase.
- D
Cost
Why wrong: Cost may be affected, but the primary immediate impact is on scope.