A project manager is evaluating a change request that would increase the project cost by 10% but reduce schedule by 15%. The change control board approves the change. What should the project manager update?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project plan and baselines

Approved changes require updating the project management plan and baselines (cost, schedule).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk register

    Why it's wrong here

    Risk register is updated for risks, not change impacts.

  • WBS

    Why it's wrong here

    WBS may need updating if scope changes, but more broadly plan and baselines.

  • Project plan and baselines

    Why this is correct

    Correct action after change approval.

  • Issue log

    Why it's wrong here

    Issue log tracks current problems.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.