PK0-005 Project Management Concepts Practice Question
A project manager is defining the project life cycle for a construction project where requirements are well-defined and unlikely to change. Which project management methodology is most appropriate for this scenario?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Predictive
Predictive (waterfall) works best when requirements are stable and phases are sequential.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Agile
Why it's wrong here
Agile is for evolving requirements; not suitable for stable, fixed-scope projects.
- ✓
Predictive
Why this is correct
Predictive methodology uses sequential phases and is ideal for well-defined requirements.
- ✗
Hybrid
Why it's wrong here
Hybrid combines elements; not necessary when requirements are clear.
- ✗
Scrum
Why it's wrong here
Scrum is an agile framework; not appropriate for fixed-scope construction.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.