A project manager is defining the project life cycle for a construction project where requirements are well-defined and unlikely to change. Which project management methodology is most appropriate for this scenario?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Predictive

Predictive (waterfall) works best when requirements are stable and phases are sequential.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Agile

    Why it's wrong here

    Agile is for evolving requirements; not suitable for stable, fixed-scope projects.

  • Predictive

    Why this is correct

    Predictive methodology uses sequential phases and is ideal for well-defined requirements.

  • Hybrid

    Why it's wrong here

    Hybrid combines elements; not necessary when requirements are clear.

  • Scrum

    Why it's wrong here

    Scrum is an agile framework; not appropriate for fixed-scope construction.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.