Courseiva
easyMultiple Choice

PK0-005 Practice Question: A project manager is in the process of developing…

A project manager is in the process of developing the project schedule. Which activity most directly determines the project's finish date?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Critical path analysis

The critical path is the sequence of tasks that dictates the project's minimum duration.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Cost estimation

    Why it's wrong here

    Cost estimation produces monetary figures for resources, not the schedule network logic that sets the finish date; duration estimation and critical path analysis do that. It tempts because cost and schedule are both planning baselines, but cost data does not determine when the last activity ends.

  • ✓

    Critical path analysis

    Why this is correct

    Critical path analysis identifies the longest sequence of dependent activities, whose total duration equals the shortest possible project completion time. Any delay on that path directly delays the finish date, so it is the activity that determines the schedule's end.

  • ✗

    Quality planning

    Why it's wrong here

    Quality planning defines standards, metrics and acceptance criteria, not activity durations or dependencies; the critical path determines the finish date. It tempts because quality activities consume schedule time, but planning them does not itself establish when the project completes.

  • ✗

    Resource estimation

    Why it's wrong here

    Resource estimation identifies the types and quantities of resources needed per activity, not their durations or sequencing; duration estimation plus critical path analysis fixes the finish date. It tempts because resource availability can extend durations, but estimation alone does not compute the completion date.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.