A project manager is in the process of developing the project schedule. Which activity most directly determines the project's finish date?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Critical path analysis
The critical path is the sequence of tasks that dictates the project's minimum duration.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Cost estimation
Why it's wrong here
Cost estimation is unrelated to the schedule finish date.
- ✓
Critical path analysis
Why this is correct
The critical path identifies the longest path through the project and directly determines the earliest possible finish date.
- ✗
Quality planning
Why it's wrong here
Quality planning defines quality standards but does not affect the finish date.
- ✗
Resource estimation
Why it's wrong here
Resource estimation influences duration but does not directly determine the finish date.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.