PK0-005 Project Management Concepts Practice Question

A project has been completed, and the project manager is conducting a lessons learned session and archiving project documents. Which project life cycle phase is being performed?

⚠ Common exam trap

PK0-005 often tests whether candidates can distinguish end-of-phase activities from end-of-project activities, and whether they recognize that lessons learned and archiving belong to Closing rather than Executing or Monitoring.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Closing

Lessons learned sessions and archiving of project documents are classic Closing phase activities. The Closing phase (or Closing Process Group) encompasses finalizing all activities across all process groups, obtaining formal acceptance, transitioning deliverables, releasing resources, and capturing organizational process assets such as lessons learned and archived records.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Initiating

    Why it's wrong here

    Initiating authorises the project and defines its high-level objectives; lessons learned and archiving happen once the product is delivered and accepted. Initiating tempts because it also generates a charter, but it would be correct at project start, not during closure.

  • ✓

    Closing

    Why this is correct

    Lessons learned sessions and document archiving occur during Closing, the final phase of the project life cycle, where deliverables are formally accepted and records are handed over. This satisfies the stem's description of post-completion administrative wrap-up activities.

  • ✗

    Planning

    Why it's wrong here

    Planning defines scope, schedule and budget before work begins; lessons learned and document archiving occur after deliverables are accepted. Planning tempts because it also produces documentation, yet it would be correct when building the project management plan, not closing the project.

  • ✗

    Executing

    Why it's wrong here

    Executing covers producing deliverables and coordinating resources; the stem describes post-completion review and archival, which belong to closing. Executing tempts because lessons learned are gathered throughout delivery, but it would be correct while work is being performed, not after completion.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.