Courseiva
Project Management ConceptseasyMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project has been completed, and the project manager is conducting a lessons learned session and archiving project documents. Which project life cycle phase is being performed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Closing

The closing phase involves formal acceptance of deliverables, lessons learned, releasing resources, and archiving documents.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiating

    Why it's wrong here

    Initiating involves authorizing the project or phase.

  • Closing

    Why this is correct

    Correct. Closing includes lessons learned and archiving.

  • Planning

    Why it's wrong here

    Planning involves defining scope, objectives, and course of action.

  • Executing

    Why it's wrong here

    Executing involves completing the work defined in the project plan.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.