PK0-005 Project Management Concepts Practice Question
A project has been completed, and the project manager is conducting a lessons learned session and archiving project documents. Which project life cycle phase is being performed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Closing
The closing phase involves formal acceptance of deliverables, lessons learned, releasing resources, and archiving documents.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Initiating
Why it's wrong here
Initiating involves authorizing the project or phase.
- ✓
Closing
Why this is correct
Correct. Closing includes lessons learned and archiving.
- ✗
Planning
Why it's wrong here
Planning involves defining scope, objectives, and course of action.
- ✗
Executing
Why it's wrong here
Executing involves completing the work defined in the project plan.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.