mediumMultiple Choice

PK0-005 Cost Performance Index (CPI) Practice Question

Network Topology
|Refer to the exhibit.

Given EV = $80,000 and AC = $90,000, what is the project's cost performance index (CPI) and what does it indicate?

⚠ Common exam trap

The trap is inverting the CPI formula (AC/EV instead of EV/AC) or misreading the threshold — candidates who compute 1.11 or who think CPI < 1 means under budget will pick the wrong option.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

CPI = 0.89; the project is over budget

CPI is calculated as EV / AC = $80,000 / $90,000 ≈ 0.89. A CPI less than 1.0 means the project is spending more than the value earned, so it is over budget. The correct answer pairs the 0.89 value with the over-budget interpretation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    CPI = 0.89; the project is under budget

    Why it's wrong here

    The 0.89 CPI is calculated correctly, but a value below 1.0 means cost overrun, not under budget; $90,000 spent against $80,000 earned is overspending. It is tempting because the numeric ratio is right, so only the interpretation needs correcting.

  • ✗

    CPI = 1.11; the project is under budget

    Why it's wrong here

    CPI is EV divided by AC, giving 80,000 ÷ 90,000 = 0.89, not 1.11; the arithmetic inverts the ratio. It is tempting because dividing AC by EV does yield 1.11, but that figure describes nothing meaningful and the under-budget conclusion is also wrong.

  • ✓

    CPI = 0.89; the project is over budget

    Why this is correct

    Dividing earned value by actual cost ($80,000 ÷ $90,000) yields a CPI of 0.89. Any CPI below 1.0 signals that each dollar spent returns less than a dollar of earned value, satisfying the stem's over-budget constraint: the project has spent more than the work completed is worth.

  • ✗

    CPI = 0.80; the project is over budget

    Why it's wrong here

    The arithmetic 80,000/90,000 yields 0.89, not 0.80; 0.80 would require AC of 100,000. It is tempting because the sub-1 index correctly signals overspend, but the stated value misreports the magnitude, so the numeric answer itself is wrong.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.