mediumMultiple ChoiceObjective-mapped
PK0-005 Cost Performance Index (CPI) Practice Question
Network Topology
Given EV = $80,000 and AC = $90,000, what is the project's cost performance index (CPI) and what does it indicate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
CPI = 0.89; the project is over budget
CPI = EV/AC = $80,000/$90,000 = 0.89. A CPI less than 1 indicates the project is over budget.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
CPI = 0.89; the project is under budget
Why it's wrong here
Incorrect. CPI of 0.89 indicates over budget, not under budget.
- ✗
CPI = 1.11; the project is under budget
Why it's wrong here
Incorrect. CPI of 1.11 is not supported by the exhibit; the actual CPI is 0.89.
- ✓
CPI = 0.89; the project is over budget
Why this is correct
Correct. CPI = 0.89, and CPI < 1 means project is over budget.
- ✗
CPI = 0.80; the project is over budget
Why it's wrong here
Incorrect. CPI of 0.80 is not supported by the exhibit; the actual CPI is 0.89.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.