Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Cost Performance Index (CPI) Practice Question

Network Topology
|Refer to the exhibit.

Given EV = $80,000 and AC = $90,000, what is the project's cost performance index (CPI) and what does it indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

CPI = 0.89; the project is over budget

CPI = EV/AC = $80,000/$90,000 = 0.89. A CPI less than 1 indicates the project is over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • CPI = 0.89; the project is under budget

    Why it's wrong here

    Incorrect. CPI of 0.89 indicates over budget, not under budget.

  • CPI = 1.11; the project is under budget

    Why it's wrong here

    Incorrect. CPI of 1.11 is not supported by the exhibit; the actual CPI is 0.89.

  • CPI = 0.89; the project is over budget

    Why this is correct

    Correct. CPI = 0.89, and CPI < 1 means project is over budget.

  • CPI = 0.80; the project is over budget

    Why it's wrong here

    Incorrect. CPI of 0.80 is not supported by the exhibit; the actual CPI is 0.89.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.