During which project phase is the project charter created and the project manager formally assigned?

⚠ Common exam trap

PK0-005 often tests the misconception that the project charter is created during Planning, but it is actually created during Initiating.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Initiating

The project charter is created and the project manager is formally assigned during the Initiating phase. This phase involves defining the project at a high level, obtaining authorization to proceed, and identifying the key stakeholders. The charter formally authorizes the project and the project manager's authority.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Planning

    Why it's wrong here

    Planning follows initiation, so the charter and project manager appointment have already occurred by then. Planning is where the charter's contents are expanded into scope, schedule and budget baselines, which is why it is tempting as the phase where project work is formally organised.

  • ✗

    Closing

    Why it's wrong here

    Closing covers final deliverable acceptance, contract closure and resource release, so the charter and manager assignment are long settled. It would be correct if the question asked where lessons learned are documented or the project is formally signed off.

  • ✗

    Executing

    Why it's wrong here

    Executing is where the work defined in the baselines is carried out and the team is managed. It would be the answer if the question asked when deliverables are produced or resources are coordinated, but the charter and manager assignment precede any execution activity.

  • ✓

    Initiating

    Why this is correct

    The Initiating phase produces the project charter, which formally authorises the project and names the project manager. This satisfies the stem's requirement that both the charter's creation and the manager's formal assignment occur in the same phase, before planning begins.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.