Question 80 of 500
Project Management ConceptsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is cost performance index (CPI) and schedule variance (SV). These are two of the core key performance indicators for project success within earned value management (EVM), where CPI measures cost efficiency by comparing earned value to actual cost, and SV tracks schedule adherence by comparing earned value to planned value. On the CompTIA Project+ PK0-005 exam, this question tests your ability to distinguish standard EVM metrics from other project data like actual cost or planned value alone; a common trap is confusing SV with simple schedule variance percentages or mistaking CPI for a schedule metric. To remember, think of CPI as “Cost Pays the Bills” and SV as “Schedule Views the Timeline”—both directly answer whether your project is on budget and on time, which are the ultimate indicators of project success.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO of the following are examples of key performance indicators (KPIs) used to measure project success?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule variance (SV)

Schedule variance (SV) and cost performance index (CPI) are both standard key performance indicators (KPIs) defined in earned value management (EVM). SV measures the difference between earned value and planned value, indicating whether the project is ahead or behind schedule. CPI measures cost efficiency by comparing earned value to actual cost, directly reflecting project budget performance.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter approval date

    Why it's wrong here

    A date is not a performance indicator.

  • Number of team meetings per week

    Why it's wrong here

    Not a standard KPI.

  • Schedule variance (SV)

    Why this is correct

    SV is a KPI for schedule performance.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Work breakdown structure (WBS)

    Why it's wrong here

    WBS is a tool, not a KPI.

  • Cost performance index (CPI)

    Why this is correct

    CPI is a KPI for cost performance.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates confuse project artifacts (like the WBS or charter) or process metrics (like meeting frequency) with true performance indicators that quantitatively compare actual progress against baselines.

Detailed technical explanation

How to think about this question

In earned value management, SV = EV - PV, where a positive value indicates ahead of schedule, and CPI = EV / AC, where a value greater than 1.0 indicates under budget. These KPIs are derived from the project's performance measurement baseline and are tracked over time to forecast project completion. Real-world project managers use CPI to predict estimate at completion (EAC = BAC / CPI) and SV to assess schedule adherence, enabling proactive corrective actions.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Schedule variance (SV) — Schedule variance (SV) and cost performance index (CPI) are both standard key performance indicators (KPIs) defined in earned value management (EVM). SV measures the difference between earned value and planned value, indicating whether the project is ahead or behind schedule. CPI measures cost efficiency by comparing earned value to actual cost, directly reflecting project budget performance.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.