mediumMultiple ChoiceObjective-mapped
PK0-005 Practice Question: In the context of risk management, what is a…
In the context of risk management, what is a trigger?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
An event that indicates a risk is imminent or has occurred.
A trigger is an event or condition that indicates that a risk is about to occur or has occurred. It serves as a warning sign that the risk response plan should be activated.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The person responsible for monitoring the risk.
Why it's wrong here
That is the risk owner.
- ✗
The residual risk after a response is implemented.
Why it's wrong here
Residual risk is the remaining risk after response.
- ✓
An event that indicates a risk is imminent or has occurred.
Why this is correct
Correct. A trigger is a warning sign.
- ✗
The strategy to respond to a risk if it occurs.
Why it's wrong here
That is the risk response strategy.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.