Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: In the context of risk management, what is a…

In the context of risk management, what is a trigger?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

An event that indicates a risk is imminent or has occurred.

A trigger is an event or condition that indicates that a risk is about to occur or has occurred. It serves as a warning sign that the risk response plan should be activated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The person responsible for monitoring the risk.

    Why it's wrong here

    That is the risk owner.

  • The residual risk after a response is implemented.

    Why it's wrong here

    Residual risk is the remaining risk after response.

  • An event that indicates a risk is imminent or has occurred.

    Why this is correct

    Correct. A trigger is a warning sign.

  • The strategy to respond to a risk if it occurs.

    Why it's wrong here

    That is the risk response strategy.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.