A project manager wants to identify the most significant causes of delays in a software development project. Which quality tool should she use to prioritize the causes based on the Pareto principle?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Pareto chart

The Pareto chart is based on the 80/20 rule, helping prioritize the most impactful issues.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scatter diagram

    Why it's wrong here

    A scatter diagram shows correlation between two variables, not prioritization.

  • Pareto chart

    Why this is correct

    Correct. A Pareto chart uses the 80/20 rule to prioritize causes.

  • Control chart

    Why it's wrong here

    A control chart monitors process variation over time.

  • Fishbone diagram

    Why it's wrong here

    A fishbone diagram identifies potential causes but does not prioritize them.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.