Courseiva
Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

During the planning phase, which three documents are typically created? (Select THREE.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk register

The WBS, risk register, and schedule baseline are all created during planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk register

    Why this is correct

    Risk register is developed during planning.

  • Work Breakdown Structure

    Why this is correct

    WBS is a planning output.

  • Project charter

    Why it's wrong here

    Project charter is created during initiating.

  • Schedule baseline

    Why this is correct

    Schedule baseline is a planning output.

  • Lessons learned

    Why it's wrong here

    Lessons learned are documented during closing.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.