PK0-005 Project Life Cycle Practice Question
During the planning phase, which three documents are typically created? (Select THREE.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk register
The WBS, risk register, and schedule baseline are all created during planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk register
Why this is correct
Risk register is developed during planning.
- ✓
Work Breakdown Structure
Why this is correct
WBS is a planning output.
- ✗
Project charter
Why it's wrong here
Project charter is created during initiating.
- ✓
Schedule baseline
Why this is correct
Schedule baseline is a planning output.
- ✗
Lessons learned
Why it's wrong here
Lessons learned are documented during closing.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.