Project Life Cycle →mediumMultiple Select

PK0-005 Project Life Cycle Practice Question

During the planning phase, which three documents are typically created? (Select THREE.)

⚠ Common exam trap

PK0-005 often tests the phase in which key documents are created, and candidates may confuse planning outputs with initiation or execution outputs.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk register

The Risk register (A) is a planning-phase artifact because it is created during risk planning to identify, analyze, and document risks along with their probability, impact, and responses. The Work Breakdown Structure (B) is produced in planning when the project scope is decomposed into deliverables and work packages, forming the basis for estimating and scheduling. The Schedule baseline (D) is also a planning output, established once the schedule is developed and approved, and it is used to measure schedule performance. The Project charter (C) is not a planning document because it is created and approved during the initiating phase, before planning begins. Lessons learned (E) is not a planning document because it is compiled throughout the project and finalized during closing, not typically created as a planning-phase output.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Risk register

    Why this is correct

    The risk register records identified risks, their probability, impact, and planned responses. It is compiled during planning as threats and opportunities are assessed, satisfying the stem's requirement for a planning-phase document that supports ongoing monitoring and response throughout execution.

  • ✓

    Work Breakdown Structure

    Why this is correct

    The Work Breakdown Structure decomposes the total project scope into manageable deliverables and work packages. It is created during planning to define what must be delivered, satisfying the stem's requirement and providing the foundation for estimating, scheduling and assigning responsibility.

  • ✗

    Project charter

    Why it's wrong here

    The project charter is produced during initiation, authorising the project and naming the sponsor and manager, before planning begins. It is tempting because the charter is a foundational document that planning activities subsequently reference and refine.

  • ✓

    Schedule baseline

    Why this is correct

    The schedule baseline fixes the approved start and finish dates against which project progress is tracked. It is produced during planning once activities are sequenced and estimated, satisfying the stem's requirement for a planning-phase document that later enables schedule variance analysis.

  • ✗

    Lessons learned

    Why it's wrong here

    Lessons learned are captured at project closure, during the closing phase, not created as planning outputs. The option tempts because lessons learned are a recognised project artefact, and reviewing prior lessons does inform planning; however, the documents produced during planning are the project management plan, requirements documentation and risk register.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.