A project manager is reviewing a change request to modify the project scope. Which TWO items should be updated in the project management plan if the change is approved?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Scope baseline
When a change is approved, the project baselines (scope, schedule, cost) and the project management plan are updated. The scope baseline and schedule baseline are part of the plan. The change log is also updated, but it is not part of the project management plan itself.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk register
Why it's wrong here
The risk register may be updated but is not part of the project management plan.
- ✓
Scope baseline
Why this is correct
Correct. The scope baseline must be updated to reflect the approved change.
- ✗
Lessons learned register
Why it's wrong here
Lessons learned are documented separately.
- ✓
Schedule baseline
Why this is correct
Correct. If the change affects the schedule, the schedule baseline is updated.
- ✗
Issue log
Why it's wrong here
The issue log is not part of the project management plan.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.