Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project manager is reviewing the project…

A project manager is reviewing the project schedule and notices that the critical path has a duration of 120 days. One activity on the critical path has a duration of 15 days and a total float of 0. If the duration of that activity is reduced by 5 days, what is the new critical path duration?

⚠ Common exam trap

The trap here is that candidates may mistakenly think reducing a critical path activity's duration does not affect the overall critical path, or they may confuse total float with free float, leading them to choose the original duration or an incorrect reduced value.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

115 days

The critical path is the longest path in the project schedule, and any delay on a critical path activity directly extends the project duration. Since the activity on the critical path has a total float of 0, reducing its duration by 5 days reduces the total critical path duration from 120 days to 115 days.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 115 days

    Why this is correct

    Reducing a critical path activity reduces project duration by the same amount.

  • 100 days

    Why it's wrong here

    The reduction is only 5 days, not 20.

  • 120 days

    Why it's wrong here

    The duration would only remain the same if the activity was not on the critical path.

  • 125 days

    Why it's wrong here

    Reducing duration cannot increase the project duration.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.