- A
The project manager must approve the change to avoid delaying the project.
Why wrong: Approval should go through the change control board.
- B
The team should implement the change immediately to meet the regulatory deadline.
Why wrong: Changes require formal approval.
- C
The change's impact on the project's schedule, cost, and scope must be analyzed.
Triple constraint analysis is essential.
- D
The change should be approved if it is within the current phase's budget.
Why wrong: Budget alone is insufficient; schedule and scope also matter.
Quick Answer
The answer is that the change's impact on the project's schedule, cost, and scope must be analyzed. This is correct because any change request impact analysis during project execution, especially for a database schema alteration, requires a formal evaluation of how the modification will affect the triple constraint—time, budget, and deliverables—along with dependencies like data integrity and testing cycles. On the CompTIA Project+ PK0-005 exam, this concept tests your understanding of integrated change control, where the project manager must assess risks before approving changes, not just technical feasibility. A common trap is focusing solely on the technical need for the schema change, ignoring the broader ripple effects on baselines. Remember the memory tip: "Triple Check the Triple Constraint"—always evaluate schedule, cost, and scope first.
PK0-005 Project Life Cycle Phases Practice Question
This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During the execution phase of a software development project, the team discovers that the database schema needs to be altered to accommodate a new regulatory requirement. The project manager is reviewing the change request. What is the MOST important factor to consider before approving the change?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
The change's impact on the project's schedule, cost, and scope must be analyzed.
Option C is correct because any change to a database schema during the execution phase of a software development project carries significant risk to schedule, cost, and scope. The project manager must perform a formal impact analysis to understand how the schema alteration affects existing data integrity, application code dependencies, testing cycles, and deployment timelines before approving the change. This aligns with the integrated change control process defined in the PMBOK Guide and is critical for maintaining project baselines.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The project manager must approve the change to avoid delaying the project.
Why it's wrong here
Approval should go through the change control board.
- ✗
The team should implement the change immediately to meet the regulatory deadline.
Why it's wrong here
Changes require formal approval.
- ✓
The change's impact on the project's schedule, cost, and scope must be analyzed.
Why this is correct
Triple constraint analysis is essential.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
The change should be approved if it is within the current phase's budget.
Why it's wrong here
Budget alone is insufficient; schedule and scope also matter.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may assume regulatory deadlines justify immediate action (Option B) or that budget alone is sufficient (Option D), but the exam tests the formal change control process where impact analysis on the triple constraint is the most important factor before approval.
Detailed technical explanation
How to think about this question
In practice, a database schema change during execution often requires updating ORM mappings, stored procedures, and data migration scripts, which can cascade into regression testing and integration testing efforts. The project manager should use a change control board (CCB) to evaluate the change request against the project management plan, including the cost baseline and schedule baseline. A real-world scenario might involve adding a new column for a regulatory identifier, which could break existing SQL queries and require re-indexing, affecting performance and deployment timelines.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Life Cycle Phases — study guide chapter
Learn the concepts, then practise the questions
- →
Project Life Cycle Phases practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: The change's impact on the project's schedule, cost, and scope must be analyzed. — Option C is correct because any change to a database schema during the execution phase of a software development project carries significant risk to schedule, cost, and scope. The project manager must perform a formal impact analysis to understand how the schema alteration affects existing data integrity, application code dependencies, testing cycles, and deployment timelines before approving the change. This aligns with the integrated change control process defined in the PMBOK Guide and is critical for maintaining project baselines.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 11, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.