Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: During the execution phase of a software…

During the execution phase of a software development project, the team discovers that the database schema needs to be altered to accommodate a new regulatory requirement. The project manager is reviewing the change request. What is the MOST important factor to consider before approving the change?

⚠ Common exam trap

Many candidates assume regulatory deadlines justify immediate action (Option B) or that budget alone is sufficient (Option D), but the exam tests the formal change control process where impact analysis on the triple constraint is the most important factor before approval.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The change's impact on the project's schedule, cost, and scope must be analyzed.

Any change to a database schema during the execution phase of a software development project carries significant risk to schedule, cost, and scope. The project manager must perform a formal impact analysis to understand how the schema alteration affects existing data integrity, application code dependencies, testing cycles, and deployment timelines before approving the change. This aligns with the integrated change control process defined in the PMBOK Guide and is critical for maintaining project baselines.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project manager must approve the change to avoid delaying the project.

    Why it's wrong here

    Approval should go through the change control board.

  • The team should implement the change immediately to meet the regulatory deadline.

    Why it's wrong here

    Changes require formal approval.

  • The change's impact on the project's schedule, cost, and scope must be analyzed.

    Why this is correct

    Triple constraint analysis is essential.

  • The change should be approved if it is within the current phase's budget.

    Why it's wrong here

    Budget alone is insufficient; schedule and scope also matter.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.