PK0-005 Practice Question: Is a key component of the project scope statement?
Which of the following is a key component of the project scope statement?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Acceptance criteria
The scope statement includes deliverables, acceptance criteria, exclusions, assumptions, and constraints. The risk register is a separate document. The change log tracks changes. The WBS is a decomposition of scope but is not part of the scope statement itself.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Change log
Why it's wrong here
The change log is a project document that records changes, not part of scope statement.
- ✗
Work breakdown structure
Why it's wrong here
The WBS is derived from the scope statement but is not a component of the scope statement itself.
- ✗
Risk register
Why it's wrong here
The risk register is a separate document from the scope statement.
- ✓
Acceptance criteria
Why this is correct
Acceptance criteria are a key component of the scope statement, defining how deliverables are accepted.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.