Courseiva

PK0-005 Project Management Concepts Practice Question

A company is undertaking a one-time initiative to develop a new mobile application with a defined budget, schedule, and scope. Which term best describes this initiative?

⚠ Common exam trap

PK0-005 often tests the distinction between projects, programs, portfolios, and operations, and candidates may confuse a one-time initiative with ongoing operations or higher-level groupings.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project

A project is a temporary endeavor undertaken to create a unique product, service, or result. This initiative has a defined budget, schedule, and scope, and is a one-time effort to develop a new mobile application, which aligns perfectly with the definition of a project. Operations are ongoing and repetitive, portfolios are collections of projects and programs, and programs are groups of related projects managed together. Thus, 'Project' is the correct term.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Operation

    Why it's wrong here

    An operation is ongoing, repetitive work sustaining existing services, whereas this initiative is temporary and unique with a defined start and end. It tempts because operations consume most organisational effort and budget, and would be correct for describing routine activities such as maintaining the deployed application after release.

  • ✗

    Portfolio

    Why it's wrong here

    A portfolio is a collection of projects, programmes and operations managed collectively to meet strategic objectives, not a single temporary endeavour. It tempts because portfolios govern investment selection and prioritisation, and would be correct if the question described the organisation's whole set of initiatives rather than one app build.

  • ✓

    Project

    Why this is correct

    A project is a temporary endeavour with a defined start and end, undertaken to create a unique product, service, or result. The stem's one-time mobile application initiative, bounded by fixed budget, schedule, and scope, matches this definition exactly, unlike ongoing operations or programmes.

  • ✗

    Program

    Why it's wrong here

    A programme is a group of related projects managed in a coordinated way to obtain benefits not available from managing them individually; this is one discrete deliverable. It tempts because large app developments often sit within programmes, and would be correct if several interdependent projects shared a common outcome.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.